Purpose:

The main entrance roadway to the Raeburn Rd Industrial units requires repairs and remodelling.

 

The intended works are to consist of the renewal of the road area to the main entrance and associated drainage repairs to the local area.

 

An open tender process was carried out, with the most economically advantageous bid being received by Brooks & Wood at a value of £214,745.70 (excl. VAT).

 

The works will be funded from existing capital budgets.

Decision:

To award the contract to Brooks and Wood Ltd.

 

Reason:

To enable works to proceed within given timescales.

Publication date: 13/05/2022

Date of decision: 09/05/2022