Decision details

OD/20/83 Clearance and Making Safe Works - Burtons Silo Building

Decision Maker: Officer Decision

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Ipswich Borough Council are proposing to carry out Clearance and Making Safe works in relation to the ex- Burtons Silo Building on the St Peters Dock Waterfront site in Ipswich.

 

Main Contractor Services are required in order to progress with the delivery of the Works.

 

Following a competitive tendering process, Clarke Demolition Company Ltd (CDC Ltd) have achieved the Most Economically Advantageous bid with a contract sum of £142,321 (excl. VAT) which will be funded from existing allocated capital budgets and represents good value for money.

Decision:

To award Main Contractor services to CDC Ltd.

 

Reason: To allow for the delivery of the Main Contractor services to now be progressed.

Publication date: 01/03/2021

Date of decision: 26/02/2021

Accompanying Documents: