Decision details

OD/20/17 New Electric Supply Pond Hall Farm

Decision Maker: Officer Decision

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The existing 3 phase power supply to Pond Hall Farm was vandalised some 2 years ago and as a result this supply was disconnected by UKPN as a network safety requirement.

 

IBC now desires to reinstate this supply conforming to all the requirements of BS 7671, as it is a conditional requirement of the sale of the site as approved by Executive.

 

A quotation has been provided by UKPN for the electrical distribution for £20,000, they will complete all electrical works to the transformer, cable runs and waterproof enclosure. It is the proposal of this decision to place the order with UKPN funded from existing budgets allocated for the project.

Decision:

To waive contract standing orders as there is only one potential provider who can provide all the services required and to place the order with UKPN.

 

Reason: To re supply the building with an Electrical supply to enable the sale of the site.

Publication date: 20/07/2020

Date of decision: 09/07/2020