OD/19/95 Eastern Gateway - New Water Supply

Decision Maker: Officer Decision

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Ipswich Borough Council are about to commence Phase 2A infrastructure works at Eastern Gateway which will involve construction of a road, utilities and drainage.

 

As part of the works, a new water supply is required to service Development Area 16

 

Anglian Water has provided a quotation for the delivery of the works of £25,194.26.

Decision:

To waive contract standing orders as there is only one potential provider and place the order for Anglian Water.

 

Reason: To allow the provision of a new water supply for the Project Rio site.

Publication date: 18/02/2020

Date of decision: 10/02/2020