OD/20/17 New Electric Supply Pond Hall Farm

The existing 3 phase power supply to Pond Hall Farm was vandalised some 2 years ago and as a result this supply was disconnected by UKPN as a network safety requirement.

 

IBC now desires to reinstate this supply conforming to all the requirements of BS 7671, as it is a conditional requirement of the sale of the site as approved by Executive.

 

A quotation has been provided by UKPN for the electrical distribution for £20,000, they will complete all electrical works to the transformer, cable runs and waterproof enclosure. It is the proposal of this decision to place the order with UKPN funded from existing budgets allocated for the project.

Decision type: Non-key

Decision status: Recommendations Approved

Wards affected: Gainsborough;

Notice of proposed decision first published: 20/07/2020

Decision due: 9 Jul 2020 by Officer Decision

Consultees

Internal consultees: MCS Officers, Property and procurement.