OD/19/42 East Villa Replacement Boiler System

The existing hot and cold-water services at East Villa have been found to be unfit for purpose due to the volume of water stored. To ensure heating and water quality is maintained the present boilers and cold-water storage tanks are to be removed and replaced with a modern closed (no tanks) system.

 

A number of quotations were sought, but due to the risk to onsite service delivery the supplier which can provide the new system the quickest was chosen, being Columbus Plumbing and Heating Services Ltd.at a cost of £102,938. This will be funded from the East Villa refurbishment budget.

 

This decision is exempted from contract standing orders as the work is required urgently.

Decision type: Non-key

Decision status: Recommendations Approved

Wards affected: Rushmere;

Notice of proposed decision first published: 02/10/2019

Decision due: 23 Sep 2019 by Officer Decision

Consultees

Internal Consultees: Head of Housing, MCS, Procurement