OD/18/23 Sproughton Enterprise Park Contractor

IBC has a requirement for Balfour Beatty to continue with design works for the Sproughton Enterprise Park Phase 1 project to continue with the construction programme before works contracts are signed.

 

Contracts will be signed following approval from Anglian Water (Section 104 Agreement to adopt foul sewer) and the Environment Agency approval for works on the river bank/consent to discharge. It is anticipated that the approvals will be granted on 16th September.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 27/09/2018

Decision due: 5 Sep 2018 by Officer Decision

Consultation process

Internal Consultees: MCS Officers and procurement.