OD/15/16 Council house refurbishment

09/07/2015 - OD/15/16 Council house refurbishment

Why it is being made listing reasons for the decision

The Maintenance and Contracts service area carried out an open procurement process using Suffolk e-sourcing for the refurbishment and adaptation of a Council property. The work allows existing Council tenants to remain in their home.

 

An order was placed to accept the most economically advantageous tender of £45,949.00; for the completion of the project by June 2015.

 

Alternative options considered and why rejected

Consideration was given to use the in-house trade workforce but this was rejected due to capacity reasons following on-going high demand for this service.

 

List any background documents

Ipswich Borough Council’s Housing Asset Management Strategy.

 

Any Crime & Disorder, Equality, Social Value in Contracts, HR, Legal, Financial, ICT or Property implications