The work has previously been identified and incorporated in Repair & Maintenance Programme and  budgeted for in 2014/15. Tenders were invited via Suffolk E Sourcing and the best offer for both price and quality was obtained from Optimum Controls Services Ltd for the sum of £24,396.

 

Condition surveys revealed that the current provision is outdated and struggles to cope with the operational needs for many of the big performances.

Publication date: 26/09/2014

Date of decision: 23/09/2014