Decision details

OD/14/19 Installation of sliding glass doors at the Tourist Information Centre

Decision Maker: Officer Decision

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The work has previously been identified and incorporated in the Repair & Maintenance Programme and budgeted for in 2014/15.

 

Currently there is excessive heat loss from the building due to a combination of poorly fitting secondary glazed double doors and the conventional church doors being open all day. the scheme is to install sensor operated, sliding glass doors immediately behind the historic oak doors to the church, thereby restricting air flow both in and out of the building. R G Carter Ipswich Ltd is the appointed Maintenance Term Contractor (MTC) for Corporate buildings (appointed for a period of 4 years from July 2013.)  The work will cost £15,621.65p

Publication date: 26/09/2014

Date of decision: 23/09/2014