Ipswich Borough Council is required to provide a new dedicated power supply to serve the incoming occupier of Plot 11 at Eastern Gateway.

 

The original quote was sought from UKPN to deliver the supply totalling £212,595.00, paid in August 2019.

 

A revised quote from UKPN was requested for a LV Main for 6 proposed streetlights to the new road.

 

The quote received was £10,412.76

Decision:

In accordance with contract standing orders to allow the contract variation to proceed as set out above.

 

Reason: To vary the contract to enable power connections to the 6nr proposed streetlights on the Phase 2A spine road.