OD/18/48 New water supply for Eastern Gateway

Decision Maker: Officer Decision

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Ipswich Borough Council are currently undertaking the first phase of infrastructure works at Sproughton Enterprise Park which involves construction of the spine road, utilities ducting and drainage.

 

As part of the works, a new water supply is required to service Plots 1 to 4 which is currently under development for LDH (La Doria).

 

Anglian Water has provided a quotation for the delivery of the works of £20,750.76.

Decision:

To waive contract standing orders as there is only one potential provider and place the order for Anglian Water.

 

Reason: To allow the provision of a new water supply for the LDH (La Doria) site.

Publication date: 24/12/2018

Date of decision: 05/12/2018