OD/18/23 Sproughton Enterprise Park Contractor

Decision Maker: Officer Decision

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

IBC has a requirement for Balfour Beatty to continue with design works for the Sproughton Enterprise Park Phase 1 project to continue with the construction programme before works contracts are signed.

 

Contracts will be signed following approval from Anglian Water (Section 104 Agreement to adopt foul sewer) and the Environment Agency approval for works on the river bank/consent to discharge. It is anticipated that the approvals will be granted on 16th September.

Decision:

To contract with Balfour Beatty for design works prior to main contract being signed.

 

Cost - £27,122.00

 

Reason: To enable works to proceed within given timescales.

Publication date: 27/09/2018

Date of decision: 05/09/2018