PH/24/13 St Lawrence Church - Main Contractor

Decision Maker: Leader of the Council: Place

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Following open tender returns, the report recommends to the Portfolio Holder for Place the appointment of a main contractor to undertake external stone repair and scaffolding works to St Lawrence Church.

Decision:

To authorise the Assistant Director of Place, in consultation with the Heads of Legal and Procurement, to award a contract for the works required to St Lawrence Church to the contractor listed as CM1 in Exempt Appendix 1 of the report.

 

Reason: To enable the works required to St Lawrence Church to be carried out.

Publication date: 26/02/2025

Date of decision: 26/02/2025

Effective from: 06/03/2025